The training signal box at Zittau Süd Station, used by the
Faculty of Electrical Engineering and Computer Science at
“
” (KIA) electrical engineering
The installation of the signals was preceded by a series of steps:
Transporting signal poles to the refurbishment workshop
Procurement of missing poles from the Cottbus Signal Works
Refurbishment of the individual components and the poles
Manufacturing and procuring defective and missing components
Manufacturing of two base plates to support the steel masts
Determination of signal locations
Installation of the ground bases
The work was primarily carried out by students from the LST department in the workshops at the Bertsdorf train station. In addition to university staff, they received technical support—for which we are very grateful—from employees of the railway operator (SOEG mbH) and the Zittauer Schmalspurbahnen e.V. association.
Although the installation of the signals marks an important milestone, the project is not yet complete. Next semester, the signals are to be connected to the training signal box. Since the signals are marked as “out of service” by a signal panel located upstream, this will not interfere with rail operations. Train traffic can proceed unimpeded regardless of the signal position. Furthermore, when students complete internships involving the setting of signals, there is no need to take the train schedule into account.
Contact:
Faculty of Electrical Engineering and Computer Science
Patrick Hornung
Research Assistant in the Control and safety technology project
Email: p.hornung@hszg.de
lst-zittau.blogspot.de/2015/07/form-einfahrsignal-des-bf-zittau-sud.html